PROJECT CUSTOMER RATING SCOPE EXPECTED

1

TENUGHAT TPS TVNL 1 X 210 MW UPGRADATION OF MILLING SYSTEM MAY '02

2

ROURKELA STEEL PLANT SAIL 1 X 25 MW DISMANTLING & ERN. OF NEW STG MAY '02

3

NAMRUP UNIT-3 HFCL PROCESS R&M OF NH3 PLANT JUN '02

4

KOLAGHAT UNIT-3 WBPDCL 210 MW RETROFIT OF TSI JUL '02

5

CHANDRAPURA TPS UNIT-1,2 & 3 DVC 3 X 120 MW RLA / PET/ R&M OF BLR., TG. & BOP JUN '02

6

CHANDRAPURA UNIT-4,5 & 6 DVC 120 MW RLA / R&M OF PLANT JAN '03

7

BOKARO-A DVC 50 MW RLA / R&M OF BOILER FEB '03

8

KOLAGHAT TPS WBPDCL 1 X 210 MW RETROFITTING OF ESP MAR '03

9

DURGAPUR D P L 1 X 110 MW RETROFITTING OF ESP MAR '03

10

DTPS/TALCHER/ KOLAGHAT/TENUGHAT  ETC DVC / NTPC / WBPDCL / DPL / TVNL ----- MISC. R & M JUL '02
TO MAR '03

11

MPSEB/SGTPS MPSEB MOD OF E-MILLS FEB '04