WELCOME TO BHEL PSER's INTERNET SITE
DISCONTINUATION OF PRACTICE OF PUBLICATION OF TENDER ADVERTISEMENTS IN NEWSPAPERS

Milestones Achieved 2018-2019
  • Punatsangchhu-1 Unit-4 (200 MW) --> Hydro Test of Spherical Valve (at 47.7 Kg/sq. cm) and High Voltage Test at 29 KV of stator completed successfully on 06/03/2019.

  • BRBCL Nabinagar Unit-3 (250 MW) --> COD was declared on 20/02/2019 by Honorable Minister of State (Independent Charge) Power, New and Renewable Energy, Shri R.K.Singh in presence of CMD NTPC, Director (Project) NTPC and GM In-charge PSER

  • NTPC Bongaigaon Unit-3 (250 MW) --> Full Load Trial Operation (72 hours) for COD have been completed successfully on 14/02/2019 at 07:45 Hrs. This has been completed in a record time after achievement of full load on 10/02/2019.

  • Bokaro A (500 MW) --> Boiler PG test successfully completed on 14/02/2019.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Unit completed 72 hours Full Load Trial Operation successfully at 05:30 Hrs. on 10/02/2019. It is the first NTPC Unit to achieve this in a minimum period of 18 days from Full Load and within 41 days from First Synchronization.

  • NTPC Bongaigaon Unit-3 (250 MW) --> The unit has been full loaded on 10/02/2019 at 00:30 Hrs.

  • Sagardighi Unit-3 (500 MW) --> Boiler PG test successfully completed on 09/02/2019.

  • Sagardighi Unit-3 (500 MW) --> Turbine PG test successfully completed on 09/02/2019.

  • Tata Steel Jamshedpur (40 MW) --> Synchronisation of STG Set achieved on 06/02/19 at 22:18 Hrs.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Turbine generator was put on barring gear on 05/02/2019 in presence of Senior RRVUNL and BHEL officials.

  • NEEPCO Monarchak (70 MW GTG & 30 MW STG) --> Combined Cycle & Open Cycle PG Test Completed successfully on 03/02/2019.

  • Punatsangchhu-1 Unit-2 (200 MW) --> Lowering of generator 2nd rotor (315 MT) completed successfully on 02/02/2019.

  • SCCL Singereni Unit-2 (600 MW) --> TG PG Test completed on 02/02/2019.

  • Punatsangchhu-1 Unit-2 (200 MW) --> Lowering of Generator Rotor (315 MT) completed successfully on 25/01/2019 in presence of MD, JMD, Director (Tech.), Director (Finance), EIC, and other officials of PHPA.

  • OPGCL IB Valley Unit-4 (660 MW) --> Synchronized successfully at 18:01 hrs on 23/01/2019.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Full Load achieved at 06.30 hrs on 23/01/2019.

  • Tata Steel Jamshedpur (40 MW) --> Turbine Rolling activity at 3000 RPM completed successfully on 22/01/2019.

  • NPGCL Nabinagar Unit-1 (660 MW) --> Synchronization with grid completed on 14/01/2019 at 02:02 Hrs. with oil firing. During the process, Safety Valve Floating of all the HRH and CRH were also completed.

  • Sagardighi Unit-4 (500 MW) --> Mill PG test successfully completed on 07/01/2019.

  • North Karanpura Unit-1 (660 MW) --> Drainable Hydro Test of Boiler at 428.1 kg/sq cm pressure completed successfully on 05/01/2019.

  • Sagardighi Unit-4 (500 MW) --> Boiler PG test successfully completed on 04/01/2019.

  • Punatsangchhu-1 Unit-1 (200 MW) --> Generator bottom bracket has been lowered in the pit on 02/01/2019. The available gap between stator bore (ID) and tip of bracket arms was very less.

  • NTPC Bongaigaon Unit-3 (250 MW) --> Synchronization completed successfully at 15:22 Hrs. on 02/01/2019.

  • BRBCL Nabinagar Unit-3 (250 MW) --> First synchronization done at 23:00 Hrs. on 31/12/2018

  • Maitree Bangladesh Unit-2 (660 MW) --> Boiler erection started on 23/12/2018.

  • RRVUNL Suratgarh Unit-7 (660 MW) --> Synchronization completed successfully on 18/12/2018 in presence of Senior RRVUNL and BHEL officials.

  • OPGCL IB Valley Unit-3 (660 MW) --> Chemical Cleaning completed successfully on 16/12/2018.

  • NSPCL Rourkela (250 MW) --> TG erection started on 15/12/2018.

  • Punatsangchhu-1 Unit-3 (200 MW) --> Lowering of Generator Stator (260 MT) successfully completed on 09/12/2018 in presence of Mr. Loknath Sharma - Chairman PHPA, Minister - Ministry of Economic Affairs (Royal Government of Bhutan), MD, JMD, Director (Tech.), Director (Finance), EIC, and other officials of PHPA-I

  • OPGCL IB Valley Unit-4 (660 MW) --> Steam Blowing completed successfully on 07/12/2018 with completion of Stage-2C. Total no. of blow given for main stages are 135.

  • IISCO Burnpur --> PG test of Turbo Blower-1 (220500 Nm3/H) alongwith its drive Turbine successfully completed on 26/11/2018 in presence of BHEL,SAIL & MECON officials.

  • IISCO Burnpur --> PG test of STG-2(18 MW) and Turbo Blower-3 (220500 Nm3/H) alongwith its drive Turbine successfully completed on 24/11/2018 in presence of BHEL, SAIL & MECON officials.

  • OPGCL IB Valley Unit-3 (660 MW) --> Boiler Light Up successfully completed on 18/11/2018 at 21:06 Hrs.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Third Stage Steam Blowing started on 17/11/2018 and completed successfully on the same day.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Second Stage Steam blowing (MS, CRH & HRH in circuit - IIA & LPBP in circuit - IIB) started on 08/11/2018 and completed successfully on 11/11/2018.

  • BRBCL Nabinagar Unit-3 (250 MW) --> First Stage Steam blowing (MS & CRH in circuit - IA & HPBP in circuit - IB ) started on 03/11/2018 and completed successfully on 06/11/2018.

  • BRBCL Nabinagar Unit-1 (250 MW) --> Mill PG Test has been completed successfully on 03/11/2018.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Turbine was successfully put on Barring gear at 23:54 Hrs. on 31/10/2018.

  • Tata Steel Jamshedpur (40 MW) --> Successfully demonstrated the test blow of Silence Steam Blowing on 25/10/2018, which is first time in BHEL history and with in-house design of BHEL.

  • Sagardighi Unit-4 (500 MW) --> ESP PG test completed on 15/10/2018.

  • OPGCL IB Valley (2 x 660 MW) --> Unit 3 TG & Unit 4 TG has been put on Barring gear at 17:05 Hrs. & 17:25 Hrs. respectively on 09/10/2018. Both TG has been put on Barring gear on the same day.

  • BRBCL Nabinagar Unit-1 (250 MW) --> SG PG Test completed successfully on 08/10/2018.

  • Punatsangchhu-2 HEP --> Assembly and Hydro Test of 1st Butter Fly (BF) valve successfully completed on 08/10/2018 at 18.50 kg / sq cm. Diameter of valve is 5.50 meters.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Boiler Alkali Flushing and Acid cleaning (including Rinsing) Started on 29/09/2018 and successfully completed on 06/10/2018.

  • OPGCL IB Valley (2 x 660 MW) --> TG Oil flushing of both units completed successfully. Unit-3 completed on 03/10/2018 & Unit-4 completed on 05/10/2018.

  • BRBCL Nabinagar Unit-1 (250 MW) --> PG Test of TG Cycle completed during the period 30/09/2018 to 04/10/2018.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Boiler acid cleaning successfully completed on 03/10/2018.

  • Punatsangchhu-1 Unit-5 (200 MW) --> Core Flux Test of Stator completed successfully on 03/10/2018 with Core Loss observed within permissible [design] limit & no Hot Spot detected for the Stator during the test.

  • Tata Steel Jamshedpur (40 MW) --> Oil Flushing declared completed by TSL on 26/09/2018.

  • Tata Steel Project Jamshedpur-->Turbine put on Barring on 26.09.2018;

  • Sagardighi Unit-3 (500 MW) --> Mill PG test completed on 18/09/2018.

  • OPGCL IB Valley Unit-4 (660 MW) --> Chemical cleaning completed successfully on 15/09/2018 at 04:30 Hrs.

  • OPGCL IB Valley Unit-3 (660 MW) --> Boiler Non Drainable Hydro Test completed successfully on 15/09/2018 at 15:50 Hrs.

  • BRBCL Nabinagar Unit-3 (250 MW) --> BLU achieved successfully on 13/09/2018.

  • Sagardighi Unit-3 (500 MW) --> ESP PG test completed on 12/09/2018.

  • NTPC Bongaigaon Unit-3 (250 MW) --> Steam Blowing completed on 10/09/2018 at 01:00 Hrs.

  • NSPCL Rourkela (250 MW) --> Boiler Drainable Hydro Test successfully completed on 08/09/2018. The same has been achieved in the first attempt.

  • BRBCL Nabinagar --> TG#3 Deck Floating Activity of BRBCL Nabinagar site has been successfully Completed on 06/09/18.

  • OPGCL IB Valley Unit-4 (660 MW) --> Boiler Light Up successfully completed on 31/08/2018 at 21:58 Hrs.

  • Punatsangchhu-1 HEP --> Hydro test of 2nd MIV successfully completed on 26/08/2018. Assembly and testing of this MIV has been completed in record time of 26 days as against L2 schedule of 40 days.

  • RRVUNL Suratgarh Unit-7 (660 MW) --> Steam Blowing successfully completed on 25/08/2018 (09:00 PM).

  • OPGCL IB Valley Unit-4 (660 MW) --> MDBFP trial run done on 23/08/2018 for the 1st time after successful interlock protection.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> GT Charging completed on 21/08/2018.

  • Mangdechhu Unit-4 (180 MW) --> Stator has been lowered in generator barrel on 12/08/2018.

  • Tata Steel Jamshedpur (40 MW) --> Lube Oil Flushing completed on 07/08/2018.

  • NTPC Bongaigaon Unit-3 (250 MW) --> First stage of steam blowing completed on 06/08/2018.

  • OPGCL IB Valley (2 x 660 MW) --> Auxiliary Boiler Alkali Boil out completed successfully on 04/08/2018.

  • IOCL Paradip --> PG Test of GT-3 & HRSG-3 completed on 01/08/2018 at 01:00 Hrs.

  • OPGCL IB Valley Unit-4 (660 MW) --> Non Drainable Hydro Test of Boiler completed successfully on 17/07/2018 and Main Steam Line Hydro Test on 28/07/2018 in presence of Asst. Director of Factories & Boilers, Odhisha.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Non-Drainable Hydraulic Test of Boiler Re-Heater circuit successfully completed at pressure of 110 Kg sq cm on 27/07/2018 in presence of Senior RRVUNL officials, BHEL officials and boiler inspector.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Non-Drainable Hydraulic Test of Boiler Super Heater circuit completed successfully at pressure of 436 Kg/cm2 on 27/07/2018 in presence of Senior RRVUNL officials, BHEL officials and boiler inspector.

  • OPGCL IB Valley (2 x 660 MW)--> Auxiliary boiler light up done successfully on 26/07/2018 at 21:43 Hrs.

  • BRBCL Nabinagar Unit-3 (250 MW) --> STG Lub Oil, Seal Oil and Control Oil flushing has been completed successfully on 26/07/2018.

  • NTPC Bongaigaon Unit-3 (250 MW) --> TG Barring gear achieved on 26/07/2018.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Pre-Boiler detergent flushing (comprising of boiler feed water, condensate and HP-LP drip pipelines) alongwith rinsing & passivation completed successfully on 23/07/2018 in presence of Senior RRVUNL and BHEL officials.

  • Maitree Bangladesh Unit-1 (660 MW) --> Boiler Erection started on 30/06/2018.

  • IISCO Burnpur --> PG test of STGs (18MW) completed successfully in presence of SAIL & MECON officials. STG-1: Completed on 19/06/2018. STG-3: completed on 27/06/2018.

  • BRBCL Nabinagar Unit-3 (250 MW) --> Detergent flushing phase – I, II, III has been completed successfully on 13/06/2018.

  • Mangdechhu Unit-3 (180 MW) --> Rotor of MHPA unit-3 has been lowered on 09/06/2018.

  • RRVUNL Suratgarh Unit-7 (660MW) --> Steam Blowing started on 09/06/2018.

  • KBUNL Muzaffarpur Unit 4 (195 MW) --> Trial Run completed on 07/03/2018, Certificate received on 31/05/2018.

  • Tata Steel Jamshedpur (40 MW) --> Turbine Boxed Up on 22/05/2018.

  • Marwa Unit-1 (500 MW)--> Successfully completed the PG test of Boiler package on 19/05/2018 in the presence of the customer (CSPGCL) and the consultant (NTPC).

  • IISCO Burnpur --> Successfully completed the PG test of Boiler-3 (200TPH) at IISCO Burnpur site on 04/05/2018 in presence of the customer (SAIL) & the consultant (MECON).

  • Punatsangchhu-1 Unit-2 (200 MW) --> Lowering of Generator Stator successfully done on its foundation on 03/05/2018.

  • RRVUNL Suratgarh Unit-7 (660 MW) --> Alkali Boil Out and Chemical Cleaning of Boiler alongwith passivation & rinsing completed successfully on 30/04/2018 in presence of Senior RRVUNL and BHEL officials.

  • Maitree Bangladesh Unit-2 (660 MW) --> Foundation work of Boiler started on 23/04/2018 in the presence of BHEL, BIFPCL & FICHTNER officials.

  • NTPC Bongaigaon Unit-1 (250 MW) --> Milling system PG test completed on 06/04/2018.

  • NTPC Bongaigaon Unit-3 (250 MW) --> BFD system Hydro Test completed on 03/04/2018.



Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Limited, is the Eastern Wing of the Company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has now crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. Add to that projects are also being executed outside India. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations.


OUR CUSTOMERS:   CSEB   DVC   NTPC   BRBCL   WBPDCL   DPL   KBUNL   HNPCL   BSEB   SCCL   RVUNL   OPGCL   OTPC   ABHIJIT   APNRL   TSPCL   CSPGCL   APGCL   TATA POWER   NEEPCO   IOCL   IISCO   BRPL   OIL   BCPL   NHPC   NPGCL   BIFPCL